Batch Status Updates
Last Updated 06/23/2026
Batch 1
Paid Units Shipped
100%
- All paid customer orders have shipped
Batch 2
Shipped
99%
- All batch 2 orders have shipped
All other orders
Shipped
24%
- This section applies to all orders placed in March 2026 or after
- Orders started shipping on week of June 1st 2026 and are continuing to ship
- We are still on track for our original quoted 8-16 week lead time (from order date)
- All orders to Virginia and Rhode Island that were placed before May 15th have been shipped
- We have ALL of the following parts in stock for every open order:
- Stripped receivers
- Top Covers
- Barrels
- Handguards
- Riflespeed gas controls
- Small parts (pins, springs, etc)
- We have SOME of the following parts
- BCG’s
- Feed Pawls
- Feed levers
- Feed trays